Completion of DCH1 HAC01-HAC06Includes GFL PNM Pods Modification
from HAC01-HAC06 of DCH1Includes GFL Cabling and Termination
from HAC01-HAC06 of DCH1Includes Temporary Fence at HAC06 to
separate Construction and Interface Activity of GG
On baseline
β Logged
%
β 2 weeks later (baseline)
DCH QA 121 Jul 2026UpcomingOn baseline0%βΈ
Data hall network QA begins, phase 1.
On baseline
β Logged
%
β 1 week later (baseline)
MDA EARLY ACCESS27 Jul 2026UpcomingOn baseline0%βΈ
Main Distribution Area becomes accessible.
On baseline
β Logged
%
β 2 weeks later (baseline)
MDA / SSNR READY11 Aug 2026UpcomingOn baseline0%βΈ
Main Distribution Area and SSNR both fully ready.
On baseline
β Logged
%
TODAY Β· 18 AUG 2026
β ~2 months later (baseline)
EFA 205 Oct 2026UpcomingOn baseline0%βΈ
Early Floor Access, phase 2.
On baseline
β Logged
%
β ~2 weeks later (baseline)
DCH QA 217 Oct 2026UpcomingOn baseline0%βΈ
Data hall network QA begins, phase 2.
On baseline
β Logged
%
β 10 days later (baseline)
FR / SC 127 Oct 2026UpcomingOn baseline0%βΈ
Facility ready / substantial completion, phase 1.
On baseline
β Logged
%
β ~11 weeks later (baseline)
FC / PCO 109 Jan 2027UpcomingOn baseline0%βΈ
Final completion / project close-out, phase 1.
On baseline
β Logged
%
β ~2 weeks later (baseline)
FR / SC 223 Jan 2027UpcomingOn baseline0%βΈ
Facility ready / substantial completion, phase 2.
On baseline
β Logged
%
β ~12 weeks later (baseline)
FC / PCO 208 Apr 2027UpcomingOn baseline0%βΈ
Final completion / project close-out, phase 2 β project ends.
On baseline
β Logged
%
β
SUBSTATION POWER ON04 Jun 2026CompleteOn baseline0%βΈ
Substation Power On
On baseline
β Logged
%
Overall
08 Apr 2027
08 Apr 2027
On baseline
π
CHW1A Key Milestone Report
Master Schedule Tracking β Baseline Contract vs Current Forecast
LIVE SCHEDULE STATUS
Overall
All Milestones
β
COMPLETED
0 Milestones
!
DELAYED MILESTONES
0
β
FINAL VARIANCE
On baseline
β€
PHASE 2 STATUS
0 Not Yet Complete
Add Milestone
Creates a new card on the timeline and the executive report.