✎ Today CUT OFF Β· 18 AUG 2026 Connecting…
You're viewing a read-only copy. Click "Enable editing" above and enter the passphrase to make changes.
Pineapple Project Β· Rev.1

CHW1A Milestone Timeline

Data center construction schedule from piling through final project close-out, across two delivery phases.

✎ Tick a milestone to mark it complete and log its completed date. Click a row to expand. Rows re-sort automatically by date, earliest on top.
08 Apr '27
Baseline finish
08 Apr '27
Forecast finish
On baseline
Finish variance
9 / 15
Completed
--
9 of 15 milestones complete (60%)
Phase 01 Phase 02 Complete Behind baseline Ahead of baseline
Phase 01 β€” Data Halls 1–4
Piling Start 01 May 2025 Complete On baseline 0%β–Έ
Data center piling and underground works begin.
On baseline
βœ“ Logged
%
GG4249 Β· Phase 01
↓ 2.5 months later (baseline)
Steel Erect Start 15 Jul 2025 Complete On baseline 0%β–Έ
Steel structure erection begins.
On baseline
βœ“ Logged
%
GG0162 Β· Phase 01
↓ 5.5 months later (baseline)
FSA, DCH 1 & 2 Sealed 03 Jan 2026 Complete On baseline 0%β–Έ
Data Halls 1 & 2 reach weathertight completion.
On baseline
βœ“ Logged
%
GG4417 Β· Phase 01
↓ 1 month later (baseline)
FSA, DCH 3 & 4 Sealed 02 Feb 2026 Complete On baseline 0%β–Έ
Data Halls 3 & 4 reach weathertight completion.
On baseline
βœ“ Logged
%
GG4419 Β· Phase 01
↓ 4 months later (baseline)
SSNR Early Access 03 Jul 2026 Complete On baseline 0%β–Έ
Security Services Network Room becomes accessible.
On baseline
βœ“ Logged
%
GG5841 Β· Phase 01
↓ 1 week later (baseline)
EFA 1 09 Jul 2026 Complete On baseline 0%β–Έ
Early Floor Access, phase 1.
On baseline
βœ“ Logged
%
GG3900 Β· Phase 01
↓ 2 weeks later (baseline)
DCH QA 1 21 Jul 2026 Complete On baseline 0%β–Έ
Data hall network QA begins, phase 1.
On baseline
βœ“ Logged
%
GG4150 Β· Phase 01
↓ 1 week later (baseline)
MDA Early Access 27 Jul 2026 Complete On baseline 0%β–Έ
Main Distribution Area becomes accessible.
On baseline
βœ“ Logged
%
GG0194 Β· Phase 01
↓ 2 weeks later (baseline)
MDA / SSNR Ready 11 Aug 2026 Complete On baseline 0%β–Έ
Main Distribution Area and SSNR both fully ready.
On baseline
βœ“ Logged
%
GG0195 Β· Phase 01
TODAY Β· 18 AUG 2026
↓ ~2 months later (baseline)
EFA 2 05 Oct 2026 Upcoming On baseline 0%β–Έ
Early Floor Access, phase 2.
On baseline
βœ“ Logged
%
GG3905 Β· Phase 02
↓ ~2 weeks later (baseline)
DCH QA 2 17 Oct 2026 Upcoming On baseline 0%β–Έ
Data hall network QA begins, phase 2.
On baseline
βœ“ Logged
%
GG4153 Β· Phase 02
↓ 10 days later (baseline)
FR / SC 1 27 Oct 2026 Upcoming On baseline 0%β–Έ
Facility ready / substantial completion, phase 1.
On baseline
βœ“ Logged
%
GG0220 Β· Phase 01
↓ ~11 weeks later (baseline)
FC / PCO 1 09 Jan 2027 Upcoming On baseline 0%β–Έ
Final completion / project close-out, phase 1.
On baseline
βœ“ Logged
%
GG---- Β· Phase 01
↓ ~2 weeks later (baseline)
FR / SC 2 23 Jan 2027 Upcoming On baseline 0%β–Έ
Facility ready / substantial completion, phase 2.
On baseline
βœ“ Logged
%
GG0250 Β· Phase 02
↓ ~12 weeks later (baseline)
FC / PCO 2 08 Apr 2027 Upcoming On baseline 0%β–Έ
Final completion / project close-out, phase 2 β€” project ends.
On baseline
βœ“ Logged
%
GG---- Β· Phase 02
Overall
08 Apr 2027
08 Apr 2027
On baseline
πŸ“ˆ

CHW1A Key Milestone Report

Master Schedule Tracking β€” Baseline Contract vs Current Forecast

LIVE SCHEDULE STATUS
Overall All Milestones
βœ“
Completed
0 Milestones
!
Delayed Milestones
0
βš‘
Final Variance
On baseline
β–€
Phase 2 Status
0 Not Yet Complete