Pineapple Project Β· Rev.1
CHW1A Milestone Timeline
Data center construction schedule from piling through final project
close-out, across two delivery phases.
β Tick a milestone to mark it complete and log its completed date.
Click a row to expand. Rows re-sort automatically by date, earliest on
top.
08 Apr '27
Baseline finish
08 Apr '27
Forecast finish
On baseline
Finish variance
9 of 15 milestones complete (60%)
Phase 01
Phase 02
Complete
Behind
baseline
Ahead of
baseline
Data center piling and underground works begin.
GG4249 Β· Phase 01
β 2.5 months later (baseline)
Steel structure erection begins.
GG0162 Β· Phase 01
β 5.5 months later (baseline)
Data Halls 1 & 2 reach weathertight completion.
GG4417 Β· Phase 01
β 1 month later (baseline)
Data Halls 3 & 4 reach weathertight completion.
GG4419 Β· Phase 01
β 4 months later (baseline)
Security Services Network Room becomes accessible.
GG5841 Β· Phase 01
β 1 week later (baseline)
Early Floor Access, phase 1.
GG3900 Β· Phase 01
β 2 weeks later (baseline)
Data hall network QA begins, phase 1.
GG4150 Β· Phase 01
β 1 week later (baseline)
Main Distribution Area becomes accessible.
GG0194 Β· Phase 01
β 2 weeks later (baseline)
Main Distribution Area and SSNR both fully ready.
GG0195 Β· Phase 01
β ~2 months later (baseline)
Early Floor Access, phase 2.
GG3905 Β· Phase 02
β ~2 weeks later (baseline)
Data hall network QA begins, phase 2.
GG4153 Β· Phase 02
β 10 days later (baseline)
Facility ready / substantial completion, phase 1.
GG0220 Β· Phase 01
β ~11 weeks later (baseline)
Final completion / project close-out, phase 1.
GG---- Β· Phase 01
β ~2 weeks later (baseline)
Facility ready / substantial completion, phase 2.
GG0250 Β· Phase 02
β ~12 weeks later (baseline)
Final completion / project close-out, phase 2 β project ends.
GG---- Β· Phase 02
Overall
08 Apr 2027
08 Apr 2027