PINEAPPLE PROJECT Β· REV.10

CHW1A KEY MILESTONE DATES

Construction of Hyperscale Data Center with 80MW capacity conisiting of 2 Phases, wherein each phase is 40MW capacity

Location: Chonburi | Land Area: 200,000 sqm |
26 Jun 2027
Baseline finish
26 Jun 2027
Forecast finish
On baseline
Finish variance
6 / 16
Completed
--
9 of 15 milestones complete (60%)
Phase 01 Phase 02 Complete Behind baseline Ahead of baseline
Phase 01 β€” Data Halls 1–4
PILING START 29 Apr 2025 Complete On baseline 0%β–Έ
Data center piling and underground works begin.sfd
On baseline
βœ“ Logged
%
↓ 2.5 months later (baseline)
STEEL ERECT START 15 Jul 2025 Complete On baseline 0%β–Έ
Steel structure erection begins.
On baseline
βœ“ Logged
%
↓ 5.5 months later (baseline)
FSA, DCH 1 & 2 SEALED 03 Jan 2026 Complete On baseline 0%β–Έ
Data Halls 1 & 2 reach weathertight completion.
On baseline
βœ“ Logged
%
↓ 1 month later (baseline)
FSA, DCH 3 & 4 SEALED 02 Feb 2026 Complete On baseline 0%β–Έ
Data Halls 3 & 4 reach weathertight completion.
On baseline
βœ“ Logged
%
↓ 4 months later (baseline)
SSNR EARLY ACCESS 03 Jul 2026 Complete On baseline 0%β–Έ
Security Services Network Room becomes accessible.
On baseline
βœ“ Logged
%
↓ 1 week later (baseline)
EFA 1 + GFL SCOPE 09 Jul 2026 Upcoming On baseline 0%β–Έ
Completion of DCH1 HAC01-HAC06Includes GFL PNM Pods Modification from HAC01-HAC06 of DCH1Includes GFL Cabling and Termination from HAC01-HAC06 of DCH1Includes Temporary Fence at HAC06 to separate Construction and Interface Activity of GG
On baseline
βœ“ Logged
%
↓ 2 weeks later (baseline)
DCH QA 1 21 Jul 2026 Upcoming On baseline 0%β–Έ
Data hall network QA begins, phase 1.
On baseline
βœ“ Logged
%
↓ 1 week later (baseline)
MDA EARLY ACCESS 27 Jul 2026 Upcoming On baseline 0%β–Έ
Main Distribution Area becomes accessible.
On baseline
βœ“ Logged
%
↓ 2 weeks later (baseline)
MDA / SSNR READY 11 Aug 2026 Upcoming On baseline 0%β–Έ
Main Distribution Area and SSNR both fully ready.
On baseline
βœ“ Logged
%
TODAY Β· 18 AUG 2026
↓ ~2 months later (baseline)
EFA 2 05 Oct 2026 Upcoming On baseline 0%β–Έ
Early Floor Access, phase 2.
On baseline
βœ“ Logged
%
↓ ~2 weeks later (baseline)
DCH QA 2 17 Oct 2026 Upcoming On baseline 0%β–Έ
Data hall network QA begins, phase 2.
On baseline
βœ“ Logged
%
↓ 10 days later (baseline)
FR / SC 1 27 Oct 2026 Upcoming On baseline 0%β–Έ
Facility ready / substantial completion, phase 1.
On baseline
βœ“ Logged
%
↓ ~11 weeks later (baseline)
FC / PCO 1 09 Jan 2027 Upcoming On baseline 0%β–Έ
Final completion / project close-out, phase 1.
On baseline
βœ“ Logged
%
↓ ~2 weeks later (baseline)
FR / SC 2 23 Jan 2027 Upcoming On baseline 0%β–Έ
Facility ready / substantial completion, phase 2.
On baseline
βœ“ Logged
%
↓ ~12 weeks later (baseline)
FC / PCO 2 08 Apr 2027 Upcoming On baseline 0%β–Έ
Final completion / project close-out, phase 2 β€” project ends.
On baseline
βœ“ Logged
%
↓
SUBSTATION POWER ON 04 Jun 2026 Complete On baseline 0%β–Έ
Substation Power On
On baseline
βœ“ Logged
%
Overall
08 Apr 2027
08 Apr 2027
On baseline
πŸ“ˆ

CHW1A Key Milestone Report

Master Schedule Tracking β€” Baseline Contract vs Current Forecast

LIVE SCHEDULE STATUS
Overall All Milestones
βœ“
COMPLETED
0 Milestones
!
DELAYED MILESTONES
0
βš‘
FINAL VARIANCE
On baseline
β–€
PHASE 2 STATUS
0 Not Yet Complete